If the application has not been determined and provided it is before the consultation expiry date, you can use the Comment on this Application button to make representations on the proposal which will be forwarded to the Case Officer. Guidance is available for making comments on a planning application here.

For further information on how to view the working file.

Please Note : The End of Public Consultation period date is based on the earliest date a decision can be made following public consultation on an application. This date is a live field and is updated throughout the application stage based on consultations, revised consultations, site notices and press advertisement dates, where required. Therefore this date is subject to change and if you are unsure or require further information you are advised to check with the Case Officer.

Application Details
Application number HPK/2018/0161 Application type Reserved Matters - Large-scale MAJOR apps
Site address Former, Bridge Mills, New Road, Tintwistle, Derbyshire, SK13 1JN Proposal Application for approval of reserved matters (except access) following outline planning permission ref. HPK/2016/0691
Applicant name Mr Ben O'Sullivan

BDW Trading Ltd Trading As Barratt Homes
Agent name

Applicant address Brindley Road, Manchester, M16 9HQ Agent address
Application status RM-APP
Received date 21/03/2018 Valid date 19/04/2018
Fee due 32381.00 Fee paid 32381.00
Determination required date 19/07/2018 Agreed extended date 05/12/2018
Case Officer Rachael Simpkin
Start of Public Consultation period 20/04/2018 End of Public Consultation period 17/05/2018
Referred to Secretary of State date Referral expiry date
Decision by Planning Committee Committee date 10/09/2018
Decision Reserved Matters - Approved Decision Date 05/12/2018
Temp permission expiry date Permission expiry date
Legal Obligation ref.

Consultations
Name Address
County Planning (Highways) Highways Section, County Hall, Matlock, Derbyshire, DE4 3AG
Tintwistle P.C The Village Hall, Sexton Street, Tintwistle, Glossop, SK13 1JN,
Environment Agency HPBC Lower Trent Area, Trentside Offices,, Scarrington Rd, West Bridgford, Nottingham, Nottinghamshire, NG2 5FA
Derbyshire Police (Crime Prevention Design) Force Designing Out Crime Officer, Derbyshire Constabulary, Cotton Lane Police Station, Derby, Derbyshire, DE24 8ZA
HPBC Environmental Health Town Hall, Buxton,
HPBC Arboricultural Officer Arboricultural Officer, Town Hall, Buxton,
HPBC Waste (Operational Services) LEEK
HPBC Housing Strategy
Cllr Pat Jenner Tintwistle Ward,
Tintwistle P.C The Village Hall, Sexton Street, Tintwistle, Glossop, SK13 1JN,
The Owner / Occupier MARISON, BANK LANE, TINTWISTLE, SK13 1NQ
The Owner / Occupier 40, NEW ROAD, TINTWISTLE, SK13 1JN
The Owner / Occupier 42, NEW ROAD, TINTWISTLE, SK13 1JN
The Owner / Occupier 44, NEW ROAD, TINTWISTLE, SK13 1JN
The Owner / Occupier 7, BRAMAH EDGE COURT, TINTWISTLE, SK13 1LN
The Owner / Occupier 2, BRAMAH EDGE COURT, TINTWISTLE, SK13 1LN
The Owner / Occupier 3, BRAMAH EDGE COURT, TINTWISTLE, SK13 1LN
The Owner / Occupier 4, BRAMAH EDGE COURT, TINTWISTLE, SK13 1LN
The Owner / Occupier 5, BRAMAH EDGE COURT, TINTWISTLE, SK13 1LN
The Owner / Occupier 6, BRAMAH EDGE COURT, TINTWISTLE, SK13 1LN
The Owner / Occupier 8, BRAMAH EDGE COURT, TINTWISTLE, SK13 1LN
The Owner / Occupier 9, BRAMAH EDGE COURT, TINTWISTLE, SK13 1LN
County Planning (Flood Risk Management)

Attachments - Click the Description to view the attachment in a new window.
Date Description
20/04/2018 Application Form
20/04/2018 472_P_BT01_Boundary Treatments Layout(3)
20/04/2018 472_P_HLL01_Hard Landscaping Plan
20/04/2018 472_P_LP01_Location Plan
20/04/2018 472_P_ML01_Materials Layout(3)
20/04/2018 472_P_PL01_E_Planning Layout(1)
20/04/2018 472_P_RS01_Refuse Strategy(3)
20/04/2018 472_P_SH01_Storey Heights Plan(3)
20/04/2018 472_P_TBT_01_ Typical Boundary Treatment Details
20/04/2018 472_S_01_Sections(2)
20/04/2018 472_SS01_Streetscapes(1)
20/04/2018 1561-01b (sheet 1 of 3)
20/04/2018 1561-02b (sheet 2 of 3)
20/04/2018 1561-03b (sheet 3 of 3)
20/04/2018 1631r1 - Odour Assessment - New Road-Tintwistle
20/04/2018 6724.01.001 Bridge Mills-Tintwistle - Arboricultural Impact Assessment.
20/04/2018 Alderney_Planning Drawing
20/04/2018 Alderney_Planning Drawing_Inc Chimney
20/04/2018 Amber 6 block_Planning Drawing
20/04/2018 Amber End_Planning Drawing
20/04/2018 Amber Mid_Planning Drawing
20/04/2018 Barton_Planning Drawing
20/04/2018 Bridge Mills - FINAL Planning Statement
20/04/2018 Bridge Mills-Tintwhistle-DAS
20/04/2018 Bridleway 2018 EARTHWORKS.DOC
20/04/2018 Chester_Planning Drawing
20/04/2018 Chester_Planning_Inc Chimney
20/04/2018 Double Stone Detached Garage(1)
20/04/2018 Ennerdale-Det_Planning Drawing
20/04/2018 Ennerdale-End_Planning Drawing
20/04/2018 Folkestone_End_Planning Drawing Inc Chimney
20/04/2018 Folkestone-End_Planning Drawing
20/04/2018 Folkstone_Det Front Gable_Planning Drawing_Inc Chimney
20/04/2018 Folkstone-Detached Front Gable_Planning Drawing
20/04/2018 Kingsville_Planning Drawing
20/04/2018 Kingsville_Planning Drawing_Inc Chimney
20/04/2018 Maidstone_Planning Drawing
20/04/2018 Queensville_Planning Drawing
20/04/2018 SCP_TravelPlan_March_2018
20/04/2018 Single Stone Detached Garage(1)
20/04/2018 T-13-1256-GA-L02_Site Investigation_AFU_._Tier Preliminary Factual Report
20/04/2018 Tewkesbury_Planning Drawing
20/04/2018 Tewkesbury_Planning Drawing_Inc Chimney
20/04/2018 Thornton_Planning Drawing
20/04/2018 Thornton_Planning Drawing_Inc Chimney
20/04/2018 Type 67 End_Planning Drawing
20/04/2018 Type 67 Mid_Planning Drawing
24/04/2018 Consultation Response Highways
08/05/2018 Consultation Response Environment Agency
14/05/2018 Consultation Response Flood Risk Management Team
14/05/2018 Consultation Response DCC Flood Risk Management Team
23/05/2018 Highways comments
31/05/2018 Consultation Response United Utilities
01/06/2018 472-P-BTL01_Boundary Treatments_AFU_._Boundary Treatments Layout_A
01/06/2018 472-P-HLL01_External Details_AFU_._Hard Landscaping Layout_A
01/06/2018 472-P-ML01_Materal Layouts_AFU_._Materials Layout_A
01/06/2018 472-P-PL01_Planning Layouts_AFU_._Planning Layout_G
01/06/2018 472-P-RS01_Planning Layouts_AFU_._Refuse Strategy_A
01/06/2018 472-P-SH01_Planning Layouts_AFU_._Storey Heights Plan_A
01/06/2018 Bridge Mills, Tintwistle - Affordable Housing Statement - 18_05_24
01/06/2018 Folkestone End - Stone - Chimney
01/06/2018 Folkestone End - Stone
01/06/2018 Folkestone Mid - Stone
01/06/2018 Folkstone Front Gable Det - Stone - Chimney
01/06/2018 Folkstone Front Gable Det - Stone
01/06/2018 Kingsville End - Stone - Chimney
01/06/2018 Kingsville End - Stone
01/06/2018 Kingsville Mid - Stone
01/06/2018 Loxley Planning Stone
01/06/2018 Maidstone End - Stone
01/06/2018 Maidstone Mid - Stone
01/06/2018 Melrose Planning Stone
01/06/2018 Queensville End - Stone - Chimney
01/06/2018 Queensville End - Stone
01/06/2018 Bridge Mills Assessments - Issued to LA 29.05.18
04/06/2018 Schedule of Information
04/06/2018 Detailed Landscape Proposals (page 1 of 3)
04/06/2018 Detailed Landcape Proposal (page 2 of 3)
04/06/2018 Detailed Landscape Proposal ( page 3 of 3)
04/06/2018 Arboricultural Impact Assessment
04/06/2018 Noise Impact Assessment
04/06/2018 SCP Technical Note, May 2018
04/06/2018 SCP Travel Plan, May 2018
24/08/2018 472_P_TBT_01_ Typical Boundary Treatment Details_ Rev A.
24/08/2018 472_S_01_Sections_Rev A
24/08/2018 472_SS_01_Streetscapes Rev B
24/08/2018 472_SS_02_Streetscapes Rev B
24/08/2018 472_SS_03_Streetscapes Rev B
24/08/2018 472_SS_04_Streetscapes Rev B
24/08/2018 472-P-BT01_Boundary Treatments_AFU_._Boundary Treatments Layout_D
24/08/2018 472-P-HLL01_External Details_AFU_._Hard Landscaping Layout_D
24/08/2018 472-P-ML01_Materal Layouts_AFU_._Materials Layout_D
24/08/2018 472-P-PL01_Planning Layouts_AFU_._Planning Layout_K
24/08/2018 472-P-RS01_Planning Layouts_AFU_._Refuse Strategy_D
24/08/2018 472-P-SH01_Planning Layouts_AFU_._Storey Heights Plan_D
24/08/2018 1561-01d (sheet 1 of 3)
24/08/2018 1561-02d (sheet 2 of 3
24/08/2018 1561-03d (sheet 3 of 3
24/08/2018 6724.01.001 Bridge Mills Arboricultural Impact Assessment
24/08/2018 AC104406-1r3 - Bridge Mills, Tintwhistle - Noise Impact Assessment
24/08/2018 SCP_17373_Technical Note_August 2018
24/08/2018 SCP_17373_Travel Plan_August 2018
31/08/2018 Consultation response Environmental Health
06/09/2018 Consultation Response Uited Utilities
12/09/2018 United Utilities 2 Restrictive parking provision
12/09/2018 Consultation Response Environment Agency 2
05/12/2018 Decision notice