If the application has not been determined and provided it is before the consultation expiry date, you can use the Comment on this Application button to make representations on the proposal which will be forwarded to the Case Officer. Guidance is available for making comments on a planning application here.

For further information on how to view the working file.

Please Note : The End of Public Consultation period date is based on the earliest date a decision can be made following public consultation on an application. This date is a live field and is updated throughout the application stage based on consultations, revised consultations, site notices and press advertisement dates, where required. Therefore this date is subject to change and if you are unsure or require further information you are advised to check with the Case Officer.

Application Details
Application number DOC/2017/0071 Application type Discharge of conditions
Site address Land At , Linglongs Road , Whaley Bridge , Derbyshire , Proposal Discharge of conditions in relation to HPK/2017/0694 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14,16, 17, 18, 19, 21, 22, 24, 26, 27, 28
Applicant name Kevin Furey
Baratt Homes
Agent name Kevin Furey
Barratt Homes
Applicant address Brindley Road , Manchester , M16 9HQ Agent address 4 , City Park , Manchester , M16 9HQ
Application status Consultations/Re-consultations issued
Received date 21/07/2017 Valid date 21/07/2017
Fee due 97.00 Fee paid 97.00
Determination required date 15/09/2017 Agreed extended date
Case Officer Jane Colley
Start of Public Consultation period End of Public Consultation period 06/08/2019
Referred to Secretary of State date Referral expiry date
Decision by Planning Committee Committee date 07/10/2019
Decision Discharge of Conditions - Approved Decision Date 13/03/2020
Temp permission expiry date Permission expiry date
Legal Obligation ref.

Consultations
Name Address
Cllr David Lomax Whaley Bridge Ward,
Cllr Kath Thomson Whaley Bridge Ward,
Cllr Shannon-Kate Thomson Whaley Bridge Ward,
Whaley Bridge Town Council Mechanics Institute, Market Street, Whaley Bridge, High Peak, SK23 7AA
Cllr David Lomax Whaley Bridge Ward,
Cllr Kath Thomson Whaley Bridge Ward,
Cllr Shannon-Kate Thomson Whaley Bridge Ward,
Cllr David Lomax Whaley Bridge Ward,

Attachments - Click the Description to view the attachment in a new window.
Date Description
04/07/2017 Public Comment Jon Hooley
04/07/2017 Public Comment Jon Hooley
15/07/2017 Public Comment Jon Hooley
07/08/2017 Public Comment Jon Hooley
17/08/2017 Superseded Drainage Calculations
17/08/2017 Superseded 466_P_01_D_Planning Layout
17/08/2017 Superseded 466-ED-01_Remediation_ TEN_._Proposed Cut and Fill_B.
17/08/2017 Superseded 466-ED-02_Drainage Layout_ TEN_._Engineering Layout_C Superseded
17/08/2017 Superseded 466-ED-18_Roads and Sewers_TEN_._Flood Route Plan_ Superseded
17/08/2017 Superseded Badger Method Statement
17/08/2017 Superseded Flood Risk Assessment
17/08/2017 Superseded Arboricultural Method Statement
17/08/2017 Superseded Bat mitigation strategy: Trees
17/08/2017 Superseded Biodiversity Management Plan
17/08/2017 Superseded Japanese Knotweed Survey & Recommendations
17/08/2017 Superseded Appendix A - Phasing Plans
17/08/2017 Superseded Appendix B - Compound Standard Detail
17/08/2017 Superseded Waste Management Plan
17/08/2017 Superseded Application form
17/08/2017 Superseded Construction Method Statement
17/08/2017 Superseded JK17-2519-01
17/08/2017 Superseded JK17-2519-02
17/08/2017 Superseded Noise Assessment Report
17/08/2017 Superseded Earthworks
17/08/2017 Superseded Geo-Environmental Report - Coal Extract
17/08/2017 Public Comment Will Mankiewicz
18/08/2017 Public Comment Rebecca Simpson
24/08/2017 Consultation Response Ecologist WL Trust
29/08/2017 consultation response unitied utilities
29/08/2017 Public Comment Jon Hooley (1)
29/08/2017 Public Comment Jon Hooley (2)
29/08/2017 Public Comment Jon Hooley (3)
29/08/2017 Public Comment Jon Hooley (4)
15/09/2017 public comment m wood
17/09/2017 public comment v o'hare
17/09/2017 public comment b hancock
21/09/2017 Public Comment Whaley Bridge Matters
21/09/2017 Consultation Response Environment Agency
21/09/2017 Consultation Response Policy
21/09/2017 Consultation Response Coal Authority
27/09/2017 public comment j hooley
10/10/2017 DCC Highway Officer
10/10/2017 Environmental Health Officer
26/10/2017 Public Commemt J F Hooley
06/11/2017 Public comment Whaley Bridge Matters
15/01/2018 Public comment Whaley Bridge Matters (2)
05/02/2018 Public Comment Jon Hooley
06/02/2018 Public comment Whaley Bridge Matters
08/02/2018 Public Comment Jon Hooley
09/03/2018 Public comment Whaley Bridge Matters (3)
05/04/2018 Consultation Response Environmental Health
10/05/2018 Public Comment Jon Hooley
11/05/2018 Public comment Martyn Wood
25/06/2018 Public Comment Jon Hooley
28/06/2018 Public Comment Jon Hooley
22/11/2018 Superseded Environmental and Geological Appraisal Report Part 1
22/11/2018 Superseded Environmental and Geological Appraisal Report Part 2
22/11/2018 Superseded Environmental and Geological Appraisal Report Part 3
22/11/2018 Superseded Environmental and Geological Appraisal Report Part 4
22/11/2018 Superseded Environmental and Geological Appraisal Report Part 5
22/11/2018 Superseded Environmental and Geological Appraisal Report Part 6
22/11/2018 Superseded Environmental and Geological Appraisal Report Part 7
22/11/2018 Superseded Environmental Report Part 1
22/11/2018 Superseded Environmental Report Part 2
22/11/2018 Superseded Environmental Report Part 3
22/11/2018 Superseded Environmental Report Part 4
03/01/2019 Consultation Response Whaley Bridge Matters
10/01/2019 Consultation Response Whaley Bridge Matters (2)
10/01/2019 Consultation Response Whaley Bridge Matters (3)
16/01/2019 WBM flooding and drainage report
16/01/2019 180128.v02 WHALEYBR Hydrological and Hydrogeological Review and Crit..
16/01/2019 Public Comment Whaley Bridge Matters
16/01/2019 Public Comment Whaley Bridge Matters
16/04/2019 Public Comment Jon Hooley
16/04/2019 Public Comment Jon Hooley
16/04/2019 Public Comment Jon Hooley
13/05/2019 Public Comment Whaley Bridge Matters
24/05/2019 Public Comment Whaley Bridge Matters (5)
30/05/2019 Public comment Jon Hooley
30/05/2019 Public comment Jon Hooley
31/05/2019 Public comment Jon Hooley (19)
31/05/2019 Public comment Jon Hooley (20)
31/05/2019 Public comment Jon Hooley (21)
31/05/2019 Public comment Jon Hooley (22)
31/05/2019 Public comment Jon Hooley (23)
01/06/2019 Public Comment Whaley Bridge Matters
01/06/2019 Public Comment Whaley Bridge Matters
01/06/2019 Public Comment Whaley Bridge Matters
01/06/2019 Public Comment Whaley Bridge Matters (9)
01/06/2019 Public Comment Whaley Bridge Matters (10)
01/06/2019 Public Comment Whaley Bridge Matters (11)
01/06/2019 Public Comment Whaley Bridge Matters (12)
11/06/2019 Revised Condition 9,10,11,12,13 - Drainage Calculations
11/06/2019 Revised Condition 9,10,11,12,13,28 - 466-ED-02_Drainage Layout - Engineering Layout
11/06/2019 Revised Condition 9,10,11,13 - 466-ED-03_Roads and Sewers - Surface Water Area Plan
11/06/2019 Revised Condition 9,10,11,12,13 - 466-ED-07_Roads and Sewers - Manhole Details Sheet 1
11/06/2019 Revised Condition 9,10,11,12,13 - 466-ED-08_Roads and Sewers - Manhole Details Sheet 2
11/06/2019 Revised Condition 9,10,11,12,13 - 466-ED-09_Roads and Sewers - Manhole Details Sheet 3
11/06/2019 Revised Condition 9,10,11,12,13 - 466-ED-10_Roads and Sewers - Manhole Details Sheet 4
11/06/2019 Revised Condition 9,10,11,12,13 - 466-ED-11_Roads and Sewers - Manhole Details Sheet 5
11/06/2019 Revised Condition 9,10,11,12,13 - 466-ED-12_Roads and Sewers - Engineering Longsections Sheet 1
11/06/2019 Revised Condition 9,10,11,12,13 - 466-ED-13_Roads and Sewers - Engineering Longsections Sheet 2
11/06/2019 Revised Condition 9,10,11,12,13 - 466-ED-14_Roads and Sewers - Engineering Longsections Sheet 3
11/06/2019 Revised Condition 9,10,11,12,13 - 466-ED-15_Roads and Sewers - Detailed Manhole Schedules
11/06/2019 Revised Condition 9,10,11,13 - 466-ED-18_Roads and Sewer - Flood Route Plan
11/06/2019 Revised Condition 9,10,11,13 - 466-ED-30_Roads and Sewers - Flow Control Details Sheet 1
11/06/2019 Revised Condition 9,10,11,13 - 466-ED-31_Roads and Sewers - Flow Control Details Sheet 2
11/06/2019 Revised Condition 9,10,11,13 - 466-ED-33_Roads and Sewers - Headwall Details
11/06/2019 Revised Condition 9,10,11,12,13 - 466-ED-35_Drainage Layout - Plot Drainage Sheet 1
11/06/2019 Revised Condition 9,10,11,12,13 - 466-ED-36_Drainage Layout - Plot Drainage Sheet 2
11/06/2019 Revised Condition 9,10,11,12,13 - 466-ED-37_Drainage Layout - Plot Drainage Sheet 3
11/06/2019 Revised Condition 9,10,11,13 - 466-ED-46_Roads and Sewers - Land Drain Deta
11/06/2019 Revised Condition 9,10,11,12,13 - 466-ED-47_Roads and Sewers - Drainage Phasing Plan
11/06/2019 Revised Condition 9,10,11,13 - 466-ED-53_Roads and Sewers - Proposed Watercourse Structures
11/06/2019 Revised Condition 9,10,11,12,13 - 5725 -FRA - Issue 2
11/06/2019 Revised Condition 10,11,13 - 466-ED-52_Roads and Sewers - Existing Watercourse Structures
11/06/2019 Note form Applicant re Conditions 9, 10, 11 and 13
11/06/2019 Revised Condition 12 - 17-132-1_Roads and Sewers - Pump Station General Arrangement
11/06/2019 Revised Condition 12 - 17-132-2_Roads and Sewers - Pump Station Kiosk and Plinth Details
11/06/2019 Revised Condition 12 - 17-132-3_Roads and Sewers - Pump Station Hazardous Zoning Layout
11/06/2019 Revised Condition 12 - Technical Submission Document
11/06/2019 Revised Condition 12 - 466-ED-17_Roads and Sewers - Pump Station Civils
11/06/2019 Revised Condition 12 - 466-ED-27_Roads and Sewers - Sewer Abandonment Plan
11/06/2019 Revised Condition 12 - 466-ED-28_Roads and Sewers - Engineering Longsections Rising Main
11/06/2019 Revised Condition 12 - 466-ED-29_Roads and Sewers - Deep Manhole Details
11/06/2019 Revised Condition 12 - 466-ED-50_Roads and Sewers - Engineering Longsections Diversion
11/06/2019 Revised Condition 14 - Coal Extract
11/06/2019 Revised Condition 14 - Site Investigation AFU Gas Risk Assessment - J-D1747-00-L3-NLC
11/06/2019 Revised Condition 14 - Earthwork Materials - R-STP3981NM-ES01
11/06/2019 Revised Condition 14 - Trial Pits
11/06/2019 Revised Condition 22 - 466-ED-06_Roads and Sewers - Highway Surfacing Plan
11/06/2019 Revised Condition 22 - 466-P-DF-01-Development Framework
11/06/2019 Revised Condition 22,24 - 466-P-PL01_Planning Layouts
11/06/2019 Revised Condition 22 - VD17501-100-01J General Arrangement
11/06/2019 Revised Condition 22 - VD17501-100-03.1E Tracking-Sheet 1
11/06/2019 Revised Condition 22 - VD17501-100-04.1D Typical Details Sheet 1
11/06/2019 Revised Condition 22 - VD17501-100-04.2C Typical Details Sheet 2
11/06/2019 Revised Condition 22 - VD17501-110-01B Contour Plan
11/06/2019 Revised Condition 22 - VD17501-120-03B Cross Sections Sheet 3
11/06/2019 Revised Condition 22 - VD17501-200-01H Site Clearance
11/06/2019 Revised Condition 22 - VD17501-500-01I Drainage Layout
11/06/2019 Revised Condition 22 - VD17501-700-01I Pavement Materials
11/06/2019 Revised Condition 22 - VD17501-1100-01I Kerbs
11/06/2019 Revised Condition 22 - VD17501-1200-01F Signs and Markings Sheet 1
11/06/2019 Revised Condition 22 - VD17501-1200-02D Signs and Markings Sheet 2
11/06/2019 Revised Condition 4 - 466-ED-CMS01-Construction Method Statement Plan 1
11/06/2019 Revised Condition 4 - 466-ED-CMS01-Construction Method Statement Plan 2
11/06/2019 Revised Condition 4 - 466-ED-CMS01-Construction Method Statement Plan 3
11/06/2019 Revised Condition 6 - LE13843 - Noise Assessment Report
11/06/2019 Revised Condition 7,8 - 466-ED-CMS01- Construction Method Statement Plan 1
11/06/2019 Revised Condition 7,8 - 466-ED-CMS01- Construction Method Statement Plan 2
11/06/2019 Revised Condition 7,8 - 466-ED-CMS01- Construction Method Statement Plan 3
11/06/2019 Revised Condition 7,8 - Appendix B - Compound Standard Detail
11/06/2019 Revised Condition 7,8 - Appendix C - Waste Management Plan
11/06/2019 Revised Condition 16 - 6270.02.003 Landscape and Ecological Mitigation Plan
11/06/2019 Revised Condition 16 - D6270.02.001J Landscape Masterplan
11/06/2019 Revised Condition 16 - D6270.02.003-012F Detailed Planting Plans
11/06/2019 Revised Condition 17 - D6270.02.002L Bird and Bat Box Location Plan
11/06/2019 Revised Condition 18 - 6270.01.001 Bat Mitigation Strategy - Trees
11/06/2019 Revised Condition 19 - 7637.001 Badger Licensing Strategy
11/06/2019 Revised Condition 21 - Japanese Knotweed Solutions Proposal
11/06/2019 Revised Condition 21 - JK17-2519-01 Japanese Knotweed Survey Location Plan
11/06/2019 Revised Condition 21 - JK17-2519-02 Japanese Knotweed Excavation Plan
11/06/2019 Revised Condition 23 - Residents Travel Pack
11/06/2019 Revised Condition 23 - Travel Plan Final Combined - SCP-17314
11/06/2019 Revised Condition 24 - 466-P-MP01- Planning Layouts Management Plan
11/06/2019 Revised Condition 27 - Coal Extract
11/06/2019 Revised Condition 28 - 466-ED-01_Remediation - Proposed Cut and Fill
11/06/2019 Revised Condition 28 - 466-ED-22 - Retaining Walls - External Levels Sheet 1
11/06/2019 Revised Condition 28 - 466-ED-23 - Retaining Walls - External Levels Sheet 2
11/06/2019 Revised Condition 28 - 466-ED-24 - Retaining Walls - External Levels Sheet 3
11/06/2019 Revised Condition 14 - 5644-R1 Site Investigation AFU Phase 1 Desktop Study (1 of 2)
11/06/2019 Revised Condition 14 - 5644-R1 Site Investigation AFU Phase 1 Desktop Study (2 of 2)
11/06/2019 Revised Condition 14 - Remediation AFU - Earthworks Strategy Report - R-STP3981NM-ES02 (1 of 3)
11/06/2019 Revised Condition 14 - Remediation AFU - Earthworks Strategy Report - R-STP3981NM-ES02 (2 of 3)
11/06/2019 Revised Condition 14 - Remediation AFU - Earthworks Strategy Report - R-STP3981NM-ES02 (3 of 3)
11/06/2019 Revised Condition 14 - Site Investigation AFU Phase 2 Site Investigation - J-D1747-00-R1-NLC (1 of 3)
11/06/2019 Revised Condition 14 - Site Investigation AFU Phase 2 Site Investigation - J-D1747-00-R1-NLC (2 of 3)
11/06/2019 Revised Condition 14 - Site Investigation AFU Phase 2 Site Investigation - J-D1747-00-R1-NLC (3 of 3)
11/06/2019 Revised Condition 14 - Environmental and Geotechnical Appraisal Report- R-STP3981NM-AR01 (1 of 6)
11/06/2019 Revised Condition 14 - Environmental and Geotechnical Appraisal Report- R-STP3981NM-AR01 (2 of 6)
11/06/2019 Revised Condition 14 - Environmental and Geotechnical Appraisal Report- R-STP3981NM-AR01 (3 of 6)
11/06/2019 Revised Condition 14 - Environmental and Geotechnical Appraisal Report- R-STP3981NM-AR01 (4 of 6)
11/06/2019 Revised Condition 14 - Environmental and Geotechnical Appraisal Report- R-STP3981NM-AR01 (5 of 6)
11/06/2019 Revised Condition 14 - Environmental and Geotechnical Appraisal Report- R-STP3981NM-AR01 (6 of 6)
11/06/2019 Revised Condition 26 - Linglongs Road Arboricultural Method Statement - 6270.001 (1 of 2)
11/06/2019 Revised Condition 26 - Linglongs Road Arboricultural Method Statement - 6270.001 (2 of 2)
11/06/2019 Revised Condition 28 - 466-ED-02_Drainage Layout - Engineering Layout
11/06/2019 Revised Condition 7,8 - Construction Method Statement
21/06/2019 Consultation Response The Coal Authority
24/06/2019 CCTV survey on existing culvert
24/06/2019 Sewers combined
03/07/2019 Consultation Response United Utilities
04/07/2019 Public Comment Jon Hooley
04/07/2019 Consultation Response Environmental Health Officer
09/07/2019 Consultation Response Derbyshire Wildlife Trust
10/07/2019 Public comment Jonathan Hooley (24)
16/07/2019 Public Comment Will Mankiewicz
16/07/2019 Consultation response DCC Flood Risk
23/07/2019 Revised Conditions 9, 10, 11, 12, 13 Drainage calculations April 2019
23/07/2019 Revised conditions 9, 10, 11, 12, 13 Drainage Layout TEN Engineering Layout Rev S
25/07/2019 Re_ DOC_2017_0071 - Discharge of conditions
25/07/2019 Review and Assessment of Flood Risk Impacts
25/07/2019 Public Comment Will Mankiewicz
30/07/2019 Consultation response HPBC Trees
01/08/2019 Public Comment Martyn Wood
01/08/2019 Public Comment Martyn Wood
01/08/2019 consultation response whaley bridge matters
02/08/2019 consultation response united utilities
08/08/2019 Consultation Response DCC Highways
09/08/2019 Consultation Response DCC Highways
14/08/2019 Revised condition 18 - Bat Mitigation Strategy
16/08/2019 Additional Details - Condition 24
16/08/2019 Additional Details - Condition 24
16/08/2019 Revised Condition 6 - Final Noise Assessment
21/08/2019 Whaley Bridge Matters United Utilities and trunk main comments
21/08/2019 Whaley Bridge Matters recent flooding and flood damage near Linglongs Road
23/08/2019 Revised condition 8 - Final - Construction Method Statament
23/08/2019 Consultation response Environmental Health
27/08/2019 Consultation Response Economy Transport and Enviroment
28/08/2019 Consultation Response United Utilities
29/08/2019 Consultation Response DCC Flood Risk
03/09/2019 Public comment Martyn Wood 3
04/09/2019 Revised condition 23 - Travel Plan
04/09/2019 Revised condition 23 - Welcome Pack
05/09/2019 Whaley Bridge Matters drainage consultee clarification
06/09/2019 Whaley Bridge Matters recent flooding photographs part 1 of 2
06/09/2019 Whaley Bridge Matters recent flooding photographs part 2 of 2
06/09/2019 Whaley Bridge Matters GWP Response
25/09/2019 Consultation Response DCC Flood Risk 3
27/09/2019 Technical Summary - Drainage
27/09/2019 Public Comment Whale Bridge Matters re Flood Risk
04/10/2019 Public comment Martyn Wood
04/10/2019 Public comment Whaley Bridge Matters Role of DCC(LLFA)
07/10/2019 Public comment Whaley Bridge Matters - E-mail from DCC to HPBC - 29th August 2019
07/10/2019 Public comment Whaley Bridge Matters - GWP report - 4th October 2019
07/10/2019 Public comment Whaley Bridge Matters -additional information and new GWP
07/10/2019 Photograph of Railway Tunnel below Hockerley estate 290919.
07/10/2019 Public comment Whaley Bridge Matters - Previous planning mistake in Whaley
13/03/2020 Decision
22/10/2021 Condition 14 Site Investigation_AFU_._Topsoil Testing Report _-_Part1
22/10/2021 Condition 14 Site Investigation_AFU_._Topsoil Testing Report _-_Part2
22/10/2021 Condition 14 Site Investigation_AFU_._Topsoil Testing Report _-_Part3
22/10/2021 Condition 14 Site Investigation_AFU_._Topsoil Testing Report _-_Part4
22/10/2021 Condition 14 Site Investigation_AFU_._Topsoil Testing Report _-_Part5
22/10/2021 Condition 14 Site Investigation_AFU_._Topsoil Testing Report _-_Part6
22/10/2021 Condition 14 Site Investigation_AFU_._Topsoil Testing Report _-_Part7